What the EIR has to fix first
You do not write a TIDP, but you decide whether the MIDP can be checked. The EIR Health Check opens on this: whether purposes and delivery milestones are declared as what, when and to whom.
Clause 5.1.3 · issued with the tender
- Information delivery milestones tied to the project programme, as a date or a stage gate rather than “at key stages”
- What each milestone is for: the decision it supports, which is what makes a late container matter
- What has to arrive at each one, by deliverable family, with its level of information need
- How long your own review and acceptance take, as a number of days the MIDP can schedule around
- How progress against the MIDP is reported to you, and how often
- What happens when a milestone is at risk: who is told, and by when